Acta Marine’s CSV-120 W2W Vessel Halfway Hull Steel Construction
Acta Marine’s new built Ulstein SX195 walk to work vessel’s hull construction passed the halfway mark this week at Crist shipyard in Poland. Work is progressing well and on schedule.
The hull construction started February 2017, and the completed hull is expected to be towed out of Crist to Ulsteinvik, Norway early November 2017. Thereafter Ulstein will complete the outfitting of the vessel and the installation of the SMST provided motion compensated gangway and 3D crane. Delivery of Acta Marine’s CSV-120 is slated for end Q1 2018. The vessel will break new grounds in workability, in-field agility, offshore logistics and comfort on board combined with a low fuel consumption.
Acta Marine intends to use the vessel in addition to its existing CSV Acta Orion on offshore wind construction projects for a variety of clients and/or related markets such as decommissioning and O&G services.