Sarens loads-out jackets for the Tyra East Future Field project


SarensDespite the COVID-19 pandemic, local restrictions, and a country-wide lockdown, Sarens performed the load-out of two jackets in Cadiz, Spain for its client Dragados Offshore.

The heavy-lift company had to load-out two jackets – TEG and TEH – for the Tyra East Future Field project. The TEH jacket weighs 5,081t and the TEG jacket weighs 7,513t. The equipment used were:

              • For the TEG jacket: 224 axle-lines and  twelve power packs
              • For the TEH jacket: 190 axle-lines and twelve power packs
              • 34 ballast pumps
              • 17 PPU
              • 18 RoRo ramps

The equipment was mobilised from the HQ in Belgium and the Netherlands by road and took around four days to reach the site, five days to assemble the SPMTs, and four days for the ballasting installation. The two jackets were transported to the quay site from the Dragados Offshore yard and loaded-out on the sea-going barge.

According to the Site Manager Teresa Diaz Carlier, “The biggest challenge during transport was to avoid any movement of the jacket to ensure that they rest perfectly on each of the support points on the barge.” She adds, “Our skilled team maneuvered the jackets with utmost precision following all COVID-19 related social distancing and health guidelines.”